How to calculate cubic yards from square feet and inches of depth

A 10 by 10 ft patio poured 4 inches thick is 1.23 cubic yards: 100 square feet times 4 inches, divided by 324. That divisor is 27 cubic feet in a yard times 12 inches in a foot. Once you have it, every cubic-yard question is area, depth and one division.

Square footage of the area first, for any shape, with cut-outs

In brief
  • Cubic yards = length (ft) × width (ft) × depth (ft) ÷ 27. Inches to feet: divide by 12.
  • Shortcut from square feet: square feet × depth in inches ÷ 324.
  • 100 sq ft is 0.62 cubic yards at 2 in, 0.93 at 3 in and 1.23 at 4 in.
  • Ready-mix is sold by the yard with minimum loads of 2 to 7 yards in four public bids; loose material by the yard or the ton; bags by the cubic foot.

The formula, and why 324 works

Volume in cubic feet is length times width times depth, all in feet. Divide by 27, the cubic feet in a cubic yard, and you have cubic yards. Depth is nearly always measured in inches, so the inch value goes through one more step first. For example, 4 inches is 4 ÷ 12 = 0.333 ft. Put the two steps together and the shortcut appears: square feet times depth in inches, divided by 324, because 27 × 12 = 324. Both routes give the same answer; the shortcut just saves a decimal.

The Mississippi State extension example runs it longhand. A 100 sq ft bed mulched 4 inches deep is 100 × 0.333 = 33.3 cubic feet. Then 33.3 ÷ 27 = 1.23 cubic yards. By the shortcut, 100 × 4 ÷ 324 = 1.23.

Measure in feet and inches, then convert

Tape measures read in feet and inches, and the inches must become decimals before anything is multiplied. Divide the inch part by 12 and add it to the feet. So 12 ft 5 in is 12 + 5 ÷ 12 = 12.42 ft, and 9 ft 10 in is 9.83 ft. Multiplying 12.42 by 9.83 gives 122.1 square feet. Multiplying 12 by 9 and ignoring the inches gives 108, a shortfall of more than a tenth before the depth is even considered. The square footage calculator takes feet and inches as two boxes so the conversion cannot be skipped.

Eight jobs, worked

Job Area Depth Cubic feet Cubic yards With 10% extra
10 × 10 ft patio slab 100 sq ft 4 in 33.3 1.23 1.36
12 × 12 ft patio slab 144 sq ft 4 in 48.0 1.78 1.96
20 × 24 ft garage floor 480 sq ft 4 in 160.0 5.93 6.52
10 × 40 ft driveway, gravel surface 400 sq ft 4 in 133.3 4.94 5.43
8 × 12 ft bed, mulch 96 sq ft 3 in 24.0 0.89 0.98
50 × 50 ft lawn, new topsoil 2,500 sq ft 6 in 1,250.0 46.3 50.9
50 × 50 ft lawn, top-dressing 2,500 sq ft 1/2 in 104.2 3.86 4.24
Raised beds, 300 sq ft in all 300 sq ft 10 in 250.0 9.26 10.19

The last column is an allowance, not a rule. Concrete is ordered 4 to 10 percent over the plan quantity on the ready-mix association's advice, and loose materials get whatever settlement the material needs. The top-dressing row shows how a small depth over a big area adds up. Half an inch over a 50 ft square is nearly four yards.

Odd shapes: split, measure, add, subtract

A shape that is not a rectangle becomes one or more that are. An L-shaped patio is two rectangles added. A bed with a curved edge is a rectangle plus a half circle, or a run of narrow rectangles measured every few feet. A circle is 3.1416 times the radius squared. A round bed 8 ft across has a 4 ft radius, so 3.1416 × 16 = 50.3 square feet. At 4 inches that is 50.3 × 4 ÷ 324 = 0.62 cubic yards.

A triangle is base times height divided by 2. A trapezoid bed 12 ft along the fence, 8 ft along the walk and 6 ft between them averages the two long sides. That is (12 + 8) ÷ 2 × 6 = 60 square feet, or 0.56 cubic yards at 3 inches. A ring of rock around a tree is the big circle minus the small one.

Depth can vary too. A bed that is 2 inches deep at the edge and 4 inches at the middle averages 3 inches. A sloped drive that needs 6 inches of base at the low end and 4 at the high end is figured at 5. Cut-outs come off the area before the depth goes on. A patio with a 4 by 4 ft planter in it is 100 minus 16, not 100.

Round to the way it is sold

Cubic yards are a volume. The order is a product with its own steps. Ready-mix concrete is sold by the cubic yard and delivered in truck mixers that hold 8 to 12 yards. Plants set minimum loads. A 2025 Tennessee city bid listed 4, 6 and 4 yards. An Oklahoma county bid opened in December 2025, for January to June 2026, listed 3, 3 and 4 yards. A New York county award listed 4 and 7 yards, with flat short-load fees of $200 to $300 under the minimum. A 2020 Missouri county sheet billed a 2 yard minimum. Its fees stepped from $125 for a 2 yard load to $25 for a 5 yard load. A 1.36 yard patio pour is a short load everywhere, so the real choice is the fee against 62 bags of mix. The association's advice is to avoid a second short load to finish a placement: order the full amount once.

Bulk gravel, mulch and topsoil sell by the cubic yard or by the ton, in whole or half yards from most suppliers. The ton quote needs the material's weight per yard to compare. Bags sell by the cubic foot and round up to the next bag. Whatever the unit, the finished layer is not the order for anything that compacts. A crushed-stone base placed 6 inches loose ends at about 4.5 inches after rolling, by Penn State's road aggregate handbook. So a base that must finish at 4 inches is ordered at 5.3. The gravel calculator keeps that allowance separate from waste so both show on the list.

Questions about calculating cubic yards

How do I convert square feet to cubic yards?

You need a depth. Multiply the square feet by the depth in inches and divide by 324. A 300 sq ft bed at 3 inches is 900 ÷ 324 = 2.78 cubic yards. Without a depth, square feet cannot become a volume.

How many cubic yards is 100 square feet?

A hundred square feet is 0.62 cubic yards at 2 inches, 0.93 at 3 inches, 1.23 at 4 inches and 1.85 at 6 inches. Each inch of depth over 100 sq ft is 0.31 cubic yards.

How do I turn cubic yards back into square feet?

Multiply the yards by 324 and divide by the depth in inches. Two cubic yards at 3 inches covers 2 × 324 ÷ 3 = 216 square feet.

Do I round cubic yards up?

Round to the step the seller uses, and always up. Ready-mix plants in four public bids set minimum loads of 2 to 7 yards, with short-load fees of $25 to $300 under them in the two bids that print one. Bulk yards sell whole or half yards. Bags round up to the next bag. Then add the waste allowance before you round, not after.

What is a cubic yard in cubic meters?

A cubic yard is 0.7646 cubic meters. A metric quote in cubic meters is bigger than it sounds: 1 cubic meter is 1.31 cubic yards.

10 source documents
  1. National Institute of Standards and Technology (NIST), Handbook 44, 2026 edition, Appendix C: 27 cubic feet = 1 cubic yard; cubic meter conversion. Read 2 November 2026.
  2. Iowa State University Extension and Outreach, How to Determine the Amount of Mulch Needed for a Garden Bed (area × depth, divide by 27). Read 2 November 2026.
  3. Mississippi State University Extension, Mulches for the Landscape, Publication 2301 (100 sq ft at 4 in = 33 cubic feet example). Read 2 November 2026.
  4. National Ready Mixed Concrete Association, CIP 31, Ordering Ready Mixed Concrete: sold by the cubic yard, truck mixers hold 8 to 12 yards, order 4 to 10 percent over. Read 2 November 2026.
  5. National Ready Mixed Concrete Association, CIP 8, Discrepancies in Yield (avoid short loads to finish a placement). Read 2 November 2026.
  6. City of Kingsport, Tennessee, Bid opening minutes, concrete, April 16, 2025: minimum delivered loads of 4, 6 and 4 cubic yards. Read 2 November 2026.
  7. Ottawa County, Oklahoma, Bid tally 2025-2026.15, ready-mix concrete, January to June 2026: minimum orders of 3, 3 and 4 yards. Read 2 November 2026.
  8. Dutchess County, New York, Award information, RFB-DCP-03-23, ready-mix concrete (extended through January 2027): minimum loads of 4 and 7 yards, flat short-load fees of $200 and $300. Read 2 November 2026.
  9. Jefferson County, Missouri, Bid tabulation, ready-mix concrete 2020: 2 yard minimum billing, short-load charges of $25 to $125 by load size. Read 2 November 2026.
  10. Penn State Center for Dirt and Gravel Road Studies, Driving Surface Aggregate Handbook, April 2025: 6 in loose compacts to about 4.5 in. Read 2 November 2026.